Pick your project and see it as phases: how many weeks each takes, what each phase costs, and what you will have paid by the end of it. It answers the question every renovation budget turns on. Free, no email.

Full house renovation: about 20.5-25.5 wk on site, £108,000 to £162,000 in total
Between the guide's times for 50 and 93 m2 I draw a straight line, so this time is my estimate.
A flat takes 8 to 16 weeks in Checkatrade's guide and a typical house five to six months in Homebuilding's. Between those sizes and above them the weeks are my estimate.
Build time only; design, permissions and builder lead time come first. Phase split is a planning guide, not a contract, and a deposit (5 to 10 percent) usually comes off the first phases rather than on top.
| Phase | Time | Cost share | Paid by end of phase |
|---|---|---|---|
| Strip-out | 2-2.5 wk | £10,800 to £16,200 | £10,800 to £16,200 |
| Structure & damp | 4-5 wk | £21,600 to £32,400 | £32,400 to £48,600 |
| First fix plumbing & electrics | 3.5-4 wk | £21,600 to £32,400 | £54,000 to £81,000 |
| Plaster | 3-4 wk | £16,200 to £24,300 | £70,200 to £105,300 |
| Kitchen & bathrooms | 5-6 wk | £21,600 to £32,400 | £91,800 to £137,700 |
| Floors & decorating | 3-4 wk | £16,200 to £24,300 | £108,000 to £162,000 |
On top of this, keep 10 to 15 percent contingency aside; surprises are normal, especially once walls or floors open.
Amounts follow the same validated guide ranges as the calculator (Checkatrade, MyJobQuote and comparable 2026 guides). Ask each trade whether VAT comes on top. What you enter never leaves your browser.
The phase table above covers every project type on this site, full house renovation included. When the quotes arrive, the quote check tells you whether they are fair. At the very end of the journey, the snagging checklist protects the final payment.
A pre-quote planner that turns your project into a build timeline: phases with weeks, money per phase and what you will have paid cumulatively, so you know what a healthy payment rhythm looks like before quotes arrive.
Because renovations fail on cash flow, not totals: the money leaves in bursts, and the biggest one often sits mid-project. Knowing what is due by the end of each phase turns a scary total into a payment plan you can check against your builder’s schedule.
They are planning guides. Every total starts from a published UK guide, and from the size you enter where the guide has a table by size: a wet room takes 4 to 7 days, a rooflight loft 4 to 6 weeks, a double storey extension of 40 m2 takes 9 to 11 weeks.
Between the sizes a guide times, and beyond its table, I work the weeks out from its own figures, and the line under the total says when that is my estimate. Windows also show the 2 to 6 weeks while the frames are made to measure. The split across phases is a practical assumption, marked as such. Your builder’s stage payments are the real schedule; this page tells you whether that schedule looks sane.
Five to ten percent, and only more for made-to-order items such as windows or kitchen units. A builder asking for half upfront is asking you to finance their previous job; pay per completed stage instead.